Week 7, Steady. 14th – 18th May 2012

Really quite steady this last week.  I’ve finished the SORs and got requests for Requests for Initial Funding (RIFs) for three projects signed off, so finally kicking those off on Wednesday/ Thursday in Runcorn.  They are:

ETAP – ALQ as discussed in previous blogs – an awesome project I’m quite excited about

Magnus – Conde Pump upgrade.  Install some new spools with double block and bleed valves; and add an integral bleed port; on to both trains on the condensate pump.

Magnus – Fire relief on Glycol boiler.  Investigate the best method of pressure relief on the Glycol boiler; currently the 1” pipes are undersized, so we need to look at some alternative options.  Mark, see Figure 1.

As for Bruce access platforms – Hugh’s got no money available at the moment so they’re on hold til the books can be rebalanced.

Right, last proof read of the TMR and then to bed.  Exciting day tomorrow as I get to play with some big cranes!  Doing a 1-day acquaint course which should be fun.  On Tuesday I’m doing Purchase Order training that will be a lot less fun.

Figure 1. Magnus Engineering Flow Diagram – Train 2

 