Home > Uncategorized > 50.0892857142857 times slower than a common snail

50.0892857142857 times slower than a common snail

Slipforming of the core at the South Bank Tower began back in May. The 12th of May to be precise. 12 floors to slipform, from +106m AOD to +154m AOD. That is 48m total.

SBT Slipform topping out

Slipforming a reinforced concrete core is supposed to be fast, efficient and financially economical. PC Harringtons (our concrete contractor) sold slipforming the core at a pace of 1.5m a day, 5 days a week. So by more complicated maths this makes:

        Duration = 48m / 1.5m per day = 32 working days, or roughly 6 weeks

Therefore,

       Date for completion = 12th May 14 + 6 weeks = 20th Jun 14

Sadly, this date for the completion of the core was not met. We topped out today! 5th Aug 14!

Thus,

       Actual duration of slipping = 5 Aug 14 – 12 May 14 = 67 working days

So,

     Actual Speed of slipform rise = 48m / 67 days = 0.71m per working day

At 10 hours work per day, this makes:

     Actual Speed of slipform = 0.71m / 10 hours = 0.072m per hour  

                                                or 72mm per hour

                                                or 1.2mm per min

                                                or 0.020 mm per second

                                                or 20 micro m per second, on average.

A common snail has a speed of 0.001m/s, or 1mm/s, or 1000micro m/s. Therefore 50 times faster than our slipform has climbed!

As I said, the planned speed (or rate) of slipping was 1.5m per day.  That makes the achieved speed of the slip 48% of the planned rate! Is this adequate? It has to be asked whether this was the most economical method of building the tower.

At the South Bank Tower we have a rare set of site conditions. The build ability of tower is generally poor, the complexity of reinforcement is high, the burden of temporary works is also high, access is limited, competition for hook time on the tower crane is high and weather conditions 150m above ground mean that it can be less than conducive to work.

I’ve decided to explore this issue in my latest TMR. What alternative systems could have been used to build the core? Should the tower have been purely steel? Additionally, should Mace have known that achieving a rate of rise of 1.5m a day was over-ambitious? And how was this reflected in the contract to deliver the slipform?

I also want to explore whether the project was influenced by the fact it wasn’t fixed price at the start, and had it been fixed would we still have taken the same decision to slip it.

Having spent the last 6 weeks inside the slip on a daily basis I can confirm it can be fraught, manic and a desperate place. There was never quiet second. PCH performed as best they could in my view. The slow pace was not due to laziness, insufficient resources or commercial will. We as Mace have driven PCH to get this core finished but the sheer complexity has denied us the rate that is normal for a slipform. Other slips on the project (10 floors high) have flown up without issue.

There is very little literature available on the rate of slipforming. Is anyone aware of any? I plan to work out the financial cost the slow slip has caused, and quantify the impact this has had to the project.

 

Categories: Uncategorized
  1. 06/08/2014 at 12:53 pm

    Decent ref ( with refs in the back) Slipforming Vertical Structures (Conc Soc) on IHS
    High rates are 150mm/hr
    So your rate isn’t that far off!

  2. rrohall's avatar
    rrohall
    06/08/2014 at 7:36 pm

    Thanks for that John. It does state 150-450mm per hour though, so our rate of 71mm per hour still seems pretty slow to me. What I didn’t mention in the blog is that three adaptions have had to be performed due to changes in the profile of the core. Investigations continue.

  3. 07/08/2014 at 7:47 am

    Hi Rich – nice piece I enjoyed reading that – I know nothing about slipforms…more please.

  4. rrohall's avatar
    rrohall
    07/08/2014 at 8:00 am

    ..with pleasure Ros. My next instalment will be about dismantling them.

  5. sipetcse's avatar
    sipetcse
    07/08/2014 at 10:06 am

    Looking forward to reading the TMR Rich.

  6. painter789's avatar
    painter789
    07/08/2014 at 7:18 pm

    Rich

    Nice blog – I am sure that snail pace is not fully CPR stuff although it does bring the issue to life.

    My point is that if you look at the slip formed tower there does not seem like much concrete to me. It looks as though you have been slip forming holes!!

    Kind Regards

    Neil

  1. No trackbacks yet.

Leave a comment