Oz PCH – Helicopter Noise Attenuation.
This pic is to entice the civils to read my blog…more on this at the end.
Introduction
This blog aims to discuss the potential issue of helicopter noise being carried throughout the building using the ductwork as a noise passage/channel. It also covers the attenuation used for the back-up diesel generators.
Problem
The helicopter pad was procured as a packaged unit but there seems to be a scope gap for ownership with its commissioning. That aside, the acoustic consultant for JHG stated a helicopter using the HLS (red line in fig 2) passes directly over AHUs housed in two non-acoustic out-houses (yellow line in fig 2) and produces noise levels of around 105 dB(A) as a point source. The (A) refers to the A-weighted sound pressure level which approximates the human ear’s sensitivity to sounds of different frequencies. Without this filtering, calculated and measured sound levels would include sounds that the human ear cannot hear, such as dog whistles (high frequency) and sounds made by large buildings with changes in temperature and wind (low frequency).
For comparison table 1 indicates where 105 dB(A) sits amongst other familiar sounds.
These particular AHUs, supplying conditioned air to the Theatre Department, have been placed outside on top of the plantroom as they wouldn’t fit inside due to layout design changes. This places them in close proximity to the rooftop HLS and are only covered, for weather protection reasons, by a non-acoustic out-house structure. Fredon, who are the plantroom mechanical fit-out subcontractors, have stated that there may be an issue with sound levels in the Theatres and that they have to conduct an assessment of the noise levels produced by a visiting helicopter to determine how much sound will travel down the air-conditioning ductwork and if they comply with the performance standard at the outlet grills.
So What?
Fredon were aware they had to conduct their own acoustic performance tests, highlighted at tender, as they knew a HLS was a design package; the situation now becoming more problematic with the re-location of the AHUs outside of the plantroom. Fredon should have factored-in the acoustic performance testing when the re-design took place instead of leaving it till now, once the ductwork installation is complete.
Solution and Possible Implications
They now need to conduct the acoustic performance test and if they don’t comply they will have to fit attenuators into the ductwork in order to reduce noise travel, commercially this will be at Fredon’s expense but could potentially hold-up commissioning and may incur delay claims from JHG. The impact could be reduced if they can fit attenuators in the plantroom directly below the AHUs on top and this would cause the least pain in terms of cost and time delays but it will depend on how much attenuation is required and how congested the plantroom is already; the alternative being to fit them further downstream in ceiling voids, that are already closed up, but this is something we and Fredon would want to avoid if at all possible.
Fredon are waiting for confirmation of the noise criteria from the design consultants NDY before continuing with the test. NDY are waiting for the client to sign-off a design departure for the criteria laid out in table 2 (red box).
NB:
7 Typical values generated by helicopter movements along defined flight paths.
8 ‘Blade Slap’ is the sharp cracking sound from helicopters, typically occurring with turns, shallow descents and flare approaching a hover.
Performance criteria are provided in Table 1 on the basis of data and modelling obtained with blade slap characteristics included.
9 Assessed in terms of the continuous equivalent LAeq level. To comply with 45dB LAeq(15 mins), the LAmax (slow) is to be less than 55 dB(A) or it can exceed LAmax (slow) 55 dB(A) for 6 minutes per hour. Further LAmax should not exceed 65 dB(A) at any time.
How Attenuators Work (Simplistically)
In simplistic terms, when fitting an attenuator in line with ductwork it requires a larger space than just the original ductwork. Fig 3 shows this including the tapered sections either side of the attenuator.

Fig 3. Attenuator. Red box showing the attenuation section with the two yellow boxes showing the tapered sections.
Theoretically and in practice an attenuator works by the noise being absorbed by the acoustic filler (wool mixture) in the solid sections with gaps between to continue to allow air flow. Due to the sections taking up space (around 40%) of the duct volume, the air velocity increases. This increased velocity creates its own noise termed ‘regenerated noise’. As long as the net noise level has reduced it is considered worth doing but engineers can get caught in the trap of the law of diminishing returns due to the increased pressure losses caused by the reduction in volume. This is caused by a pressure change/differential between the point before and after the attenuator. This results in second and third order effects of requiring a higher fan speed to overcome the pressure losses and then requiring a bigger fan motor which uses more electricity. A way to resolve this is by maintaining the pressure over the attenuator which can be achieved by ensuring the attenuator is the same volume as the ductwork leading up to it. Due to the space taken up by the acoustic filler sections inside the attenuator, means that the overall dimensions of the attenuation section has to increase, as shown in fig 3. Sometimes this causes issues if there is limited space in a ceiling void.
A Different Example – Diesel Generator Noise Attenuation
I had a look around one of the 3 x 1.25 MVA back-up diesel generators to investigate its noise attenuation design.
The generators, manufactured by Cummins, are housed in individual acoustic and weather protected containers.
Inside the container, at both ends, are the attenuation sections as shown in fig 4. These are vertical sections (red line) with a permeable membrane filled with acoustic noise damping wool. At this end outside fresh air is being drawn in (blue arrows) by the generator radiator fan but the noise is escaping (yellow lines) through the gaps between the acoustic sections.
Fig 5 shows the incoming outside air (blue arrows) and the noise path (yellow lines) taken as it bounces between the two acoustic sections losing noise as it passes through the acoustic material and finally out the louvres at the end.
The capping louvers at the container end have acoustic foam attached to the underside of each horizontal louver and so also acts to reduce noise coming out (yellow lines in fig 6) but allows fresh air to be drawn in (blue arrows).
We are currently waiting for the generators to be run-up and tested with the installed fuel supply system and for all three to be tested for load sharing as part of system commissioning. Until that time we cannot fully test the acoustic noise levels produced.
Useful References
BSRIA – A Guide to HVAC Building Services Calculations (2007) (second edition) p.125 – 133, describes the acoustic calculations required in design, in particular ductwork noise transmittance.
CIBSE Guide B – Heating, Ventilating, Air Conditioning and Refrigeration (2005) – Section 5 Noise and Vibration Control for HVAC p. 5-1 to 5-22.
In Other News
For the civils, the below pics are from the final basement concrete pour filling the ground slab where one of the tower cranes once stood. Fill your boots to ask questions but I most likely won’t know the answers…I just took the pictures!
And finally…speechless!













Fran, does the spec stipulate a type of helicopter for which the noise levels must be achieved or is it an absolute standard? If it is the latter, I would be getting the smallest, lightest, quietest helicopter I could find in Australia to use during the noise measurement tests.
Jim,
The spec only stipulates the max dB value for specific locations throughout the building. For theatres this is 45 dB, so yes a Gazelle would do nicely but in all honesty I think the subcontractor should use the exact air ambulance used in WA; a Bell 412 EP produces 96 dB (A) on landing. So, Fredon need to attenuate for 51 dB(A) by time the noise travels to the Theatres.
Thanks for the interesting bits Fran – PPE doesn’t meet UK recommendatiosn for pumped concrete – Norm is resistant coveralls, usually plastic zoot suits, and eye protection. THere is also a recomendation that tops of boots should be closed over (taped or draw cord) to avoid concrete burns to feet. This is a very small pour so risks are lower and I could forgive not taping boots but I wonder about the leg wear of the hose controller! Any idea why there is a cut out pit being retained?
Richard, thanks for the PPE regs – I’ll have a check of JHG’s H&S policy and see what it says. No idea what the pit is for.
Thanks Fran. And yes the duct work noise damping was interesting too! Presumably at 40% volume reduction the permaebility drop/resistance to flow from the filler is greater due to turbulance? or is 40% an equivalent area that takes account of all that?
Correct, the 40% volume reduction creates increased resistance as the air flows through the attenuator filler material causing turbulence and thus reduces the noise. That’s why increasing the overall attenuator section area ensures the equivalent volume (which needs to be 40% larger) is similar to that of the ductwork volume either side thus reducing the velocity increase which can increase noise thereby having an adverse affect.
Thankfully they use a 4 blade Bell, the old 2 blade version is bloody noisy and I suspect you’d have a much greater issue to deal with!
The Bell is, according to a study by the design consultants, one of the noisiest emergency air ambulances in use.
They’re a nightmare, noisy and downwash but the one you have is 1000% better than the twin (classic huey, ‘Nam’ style).
Got the message Olly – you were in Aus with 2 blade Bells. Now go and build a bridge!
Wrong, never seen one in Aus. The Americans use them, come on Richard…I though you used to wear uniform! Besides, it’s started raining…no one wants to build a bridge in the rain!
Fair call. I’d presumed that after staring in Apocalypse Now there might have been some kicking around down under. Could you blog some pictures of your bridge from your dry(ish) portacabin and tell me a little about your formwork and the fixing of PS tendons – Neil has returned with tidings of great endeavour and, although I could just come and look, it would be nice to share.
(Best Michael Caine voice) Did you know that the energy stored in the huge two blade rotor of the Huey is so great, it is the only helicopter in the world that can climb during the initial stages of an engine failure? You can also land anywhere you want in a forest and have fire wood for cooking after you land.
“My name is Michael Paine (Paul Whitehouse version) and I am a nosey neighbour. Now, did you know that it takes a man in a tweed suit five and a half seconds to fall from the top of Big Ben to the ground? Now there’s not many people that know that!”
Fran, Can I assume that when the design was changed to placing the AHUs outside, a ‘Project Change Notification’ was signed to cover the extra cost of the change? Would the change notification included the requirement to carry out additional acoustic testing or is it assumed that the testing is still covered under the original tender?
If, following testing, there is a requirement to attenuate the sound level, would acoustic housing surrounding the AHU on the roof be considered? as you only mention attenuators in the duck work; that might remove any potential delay to commissioning?
Mike,
I haven’t followed through the full contractual implications but it could be traced all the way back to the client instigating the variation. Either way the design change was in play before the plantroom equipment was fully installed so they hadn’t conducted any acoustic testing at that point. Fredon were also waiting on NDY to confirm the helicopter noise test criteria. Therefore, this acoustic testing is part of the original tender.
However, apparently Fredon have completed computer modelling and so have a current design result, but they were withholding it until NDY respond to an RFI regarding exact test criteria from Fredon. This sounds suspicious to me and like they might fudge the modelling results if the criteria result is not to their liking. We have instructed Fredon to present their modelling results so we’ll soon see.
If they do need to add attenuation, you’re right in saying add it to the out-houses; this also ties in with best practice in treating noise attenuation as close to the source as possible.
There is another situation where again out-houses were required to house AHUs but these are adjacent to the plantroom (a different one from that discussed before) they were supposed to be in. These in particular are about 25 – 30 m from the entry point to the plantroom and so in this case attenuation of the out-house may not solve the issue. This is because the weather proof ductwork would still be exposed to helicopter noise (as it’s outside of the out-house) and therefore better to place the attenuator in the ductwork as it enters the plantroom. This particular area isn’t directly below the helicopter flight path and there is shielding from the two stories adjacent, so there might not be an issue; we won’t know until the modelling results have been reviewed.