Archive

Archive for 16/01/2017

The Most Dangerous Dam in the world

 

MosulDam-July2012-01.JPG

Please forgive the blatant plagiarism.  I saw these article and found it very interesting.  The British Base in  Iraq is 2 hrs away from this Dam.  While work has been done by USACE this could involve an STRE at some point in time.  The real danger point is April when the Snow Melt from Turkey hits the reservoir.

I look forward to a discussion on this topic at the Southern Hemisphere PET symposium this weekend.

New Yorker-Article Mosul Dam

Al Jazeera-Worse than a nuclear bomb

Guardian Article

Categories: Uncategorized

The Importance of Risk Registers

I am coming to the end of my Phase 2 attachment and I have been lucky to have witnessed the majority of a contract that I planned, tendered and wrote the contract for be completed on site.  However, things have not gone exactly gone to plan!

One issue with my package, which is a package to install all heavy plant in the Energy Centre and Tunnel, is that it was planned and tendered before most of the plant equipment had been procured and before the RIBA Stage 4 design had been completed.  This meant that under the subsequent stage 5 design, plant positions have changed and the plant itself has generally changed in size and weight.

These changes have pushed the some of the required works out of scope and so the sub-contractor has asked for an instruction to undertake the works and of course extra cash!  A saving grace is that I identified this as a risk back in May 16 and so entered it onto the package risk register with an allocated risk of £50,000.  On my project, all package risk is pre-allocated by the client with a risk pot allocated for each package.  Sadly, not all of the risk I identified was approved by the Client as the Client has decreed that no package risk allocation is to be greater than 5% of the package total which reduced the available risk available for scope changes due to stage 5 design changes from £50,000 to £11,000 – which is not a lot.  I do not agree with this approach as some packages will always be high risk and with no means of mitigating this risk to an acceptable level.  Therefore the Client is not suitably preparing for future increased costs.

One example of these changes moving a task out of scope and requiring a change request was the installation of the five Cooling Towers on the roof of the Energy Centre.  In this case both the position of the cooling towers changed just two weeks before the lift and the mass of the heaviest lift also increased from 5T to 10T as the selected supplier had a different method of installation to that used to estimate the cost of install.  The combination of these changes meant that the allocated 150T crane would not be sufficient to suspend the load at the required radius and so a 500T crane was required.  A 500-ton cranes requires two additional flatbeds to set and an additional set up fee of £25,000 plus an extra £3,00o for each additional day.

img_0839

These additional costs were first highlighted to the Client using the Early Warning System and I submitted a change request for an additional £28,000.   I had to brief this to the Client and explain why this had not been identified during tendering and eventually the Client agreed to use £11,000 from the risk pot and to publish an instruction with a cost value of £17,000.  This meant that the works could go ahead but it has highlighted to me the importance of trying to confirm the scope early or at least over-estimating the scope (e.g oversize the plant) to reduce risk.  That said, over-estimating in a fixed price-contracting  will  inevitably result in larger contract sums and so it is a balancing act to ensure an overall saving for the Client.

It has also demonstrated to me the importance of investing time into the Risk Register since if used correctly, the allocated risk pot can help get you out of a sticky situation and can be a useful source of funds if your scope proves to be insufficient.  Ultimately all construction work will involve risk and it is important to both correctly and accurately identify this risk, mitigate it where possible and then allocate project funds to any residual risks.  I would recommend pre-allocating funds to all residual risks so the money can be spent as soon as the risk materialises as any delays securing funds through change control will likely take time (at least a week on my site) and this in turn will likely increase overall costs and impact the all-important programme.

Anyway the cooling towers were successfully installed with the 500-ton crane:

img_0834

img_0840

But unfortunately I was not happy with the install during the QA inspection due to the misalignment of the Anti-Vibration Mounts (AVMs) and so raised this an issue with the sub-contractor.

img_0837

During the inspection I identified that the AVMs were incorrectly handed which was causing the AVMs to rotate.  I therefore got the supplier to visit site to inspect them and they have since admitted fault and will be replacing the AVMs in March/Apr – a task that will likely fall to Will Stott to lead on during his attachment – enjoy!

Categories: Uncategorized

Great Idea

I saw this in an email from a director while working in a design consultancy and thought what a great idea to generate work. Suggest something similar within the organizations you work for and claim it as your own idea….even earn yourself an Omega watch?

 

NDY Perth recently offered to update the engineering standards for the University of Western Australia (UWA) – I assume this was done at no or very little cost? This provided the university (a huge organization with enormous amounts of real estate) with up to date building/maintenance codes for which any contractor working on their site must conform to – it forms part of the initiating contract between the university and any third party contractor. In return, NDY reap the rewards of consulting on any large future projects the university carries out. Assuming UWA appoints them!! Great business methods and one in which could be applied to any large organization that maintains real estate.

Unrelated and just for fun: A friend and I were playing around with a time lapse camera this Christmas – he produced this. Pretty cool…?

 

Categories: Uncategorized