With Great Power(Point) Comes Great Responsibility!
A quick blog about conflicting relationships on my design project.
(Credit to Glynn Tomsett for the title)

I am currently working on a project which involves developing a base concept design for upgrading the Melbourne Airport short stay car park, serving Terminals 1-3, in line with a wider airport expansion programme.
The design includes re-configuration of the current floor plans to include pick-up and drop-off, additional entry and exit ramps to cater for increased traffic flow and development of pedestrian access to the terminals.
The client, Melbourne Airport, engaged my design consultant along with an architectural firm to take on the work late last year. They subsequently contracted a PM firm to manage the project.
I attended an interim client meeting a week or two ago, which involved the design consultant (us) and architects presenting their ‘optioneering’ to the PM team ahead of delivery to Melbourne Airport’s Board of Directors. During the presentation it became apparent that we were pulling in slightly different directions from the architect, who was eager to push the ‘all singing all dancing option’ with a new orientation space (structure) in front of the car park and 2 new fandangled pedestrian bridges. It might have been that there were 20+ bodies crammed into a single glazed room with broken air-conditioning on a sweltering Melbourne day, but I could definitely sense a bit of tension in the air, so I did a bit of digging.
It turns out that when we were originally engaged on the project with the architect there was no direction on who was to lead the design effort so both parties went off in their own direction. Predictably, the architects came up with a number of flowing designs that boasted ‘confluences’ and ‘spaciality’ etc, but which required extensive structural work and in some instances were unfeasible.
By all accounts they did not take kindly to the engineering advice from Aurecon about the feasibility of some of their ideas and this caused some early conflict between the parties. It wasn’t until the PM firm were engaged that the matter was resolved after they appointed Aurecon the lead coordinator of the design effort.
From what I have seen however, this hasn’t stopped the architect from attempting to force their ideas on the project and they are obviously keen to retain as much influence/control over the design as possible, including what information gets delivered to the client.
Following the meeting I attended, the PM team identified quite a few areas in the presentation that needed further development and tightening up ahead of delivery to the Melbourne Airport Board of Directors. It was agreed that the architect who had compiled the original presentation would send it through to us work on update. What followed was a frantic 1 1/2 days of pulling together the required information ahead of the meeting.
The team were literally working to get the presentation up to scratch right up to the minute the taxi arrived to pick them up. I didn’t attend this meeting, however, when the design manager got there the architect had already arrived and had a presentation on the screen ready to go. When she explained that she had the updated presentation which the team had worked hard on, the architect refused point blank to swap it over and after some discussion (conscience not to cause a scene in front of the client) she ceded and the presentation was delivered using the original version which had only a few minor amendments made by the architect.
I was quite surprised at this level of childish behavior, an indication I suppose of the architect’s need to maintain some control over the project to justify their position and inject as much architectural scope as possible.
I wondered if anyone else had any other anecdotes about conflicts between parties from their placements?
I read this whilst train-bound to meet the architects on my prison project.
1. Can’t tell you any more details as the civies think working on a prison is super secret. They made a really big deal about being vetted to work on it. SC doesn’t only allow you to do armoury checks – they think I’m bad ass…
2. 2 weeks ago, this same coordination meeting almost turned into a playground scrap. No client present but PM, Architects, Str Engr (Arup / Me), and some M&E punters.
3. Afterwards I asked who was meant to be chairing that?? Response, “think it was the architects…”. Nobody knew and as a result I experienced the same pulling in different directions as you describe. I get that it takes a while to settle into new team structures but apparently this has been going on for months!
4. This week the meeting ‘agenda’ is meant to focus on VE solutions. We’ve gone £20m over budget and looking for savings. Hot topic today should be the structural frame. Arup completed stage 4 design of steel frame in January. I have been working on an alternate pre-cast option. It looks like this re-design is still too expensive and we might now go in situ RC…
5. So here’s the BLUF/BLAB; I’ve seen similar inefficiency through lack of leadership. Interesting learning experience. I wonder if anyone will step up today…
I am aware of an SO2 Infrastructure advisor and STRE 2ic having a similar policy difference issue with some air cooling for the RAF. One promising certain things to the client, the other pointedly refusing to deliver contrary to funding policy. After some discussion there was an agreed way forward. When time came to present to the client, one party declared immediately before hand that there were a few changes to the slides but not to worry, they would handle it. Funnily enough their point of view had been substituted for the agreed way forward and the client were again promised the moon on a stick. The 2ic stayed quiet and fumed inwardly – same cap badge despite treachery. Even in the green!