Bridge over troubling roofs (Part 1)

21/05/2019 1 comment

Hello all, the Pier 6 extension at Gatwick is still going through the RIBA 3 design stage so I thought I’d switch fire to another project in the pipeline. The International Departure Lounge (IDL) link bridge is due to be built at Gatwick in the third quarter this year. It is still in the RIBA 4 design stage with the awarded works contractors now looking at the detailed design. The purpose of the bridge is to provide a more direct route between the new code F site at Pier 5 (see my first blog post) and the departure lounge. In short it is intended to improve passenger flow to the new A380 aircraft stand. At the moment passengers have to walk an indirect route to access the Pier 5 stands which adds additional walking time, reducing flow.

The construction of the bridge presents some interesting challenges as it is to be located in a heavily built up part of the airport. As can be seen in Figure 1 below, the location of the bridge is difficult to access for plant and equipment. Crane access is also difficult due to the size of the existing buildings, limiting prefabrication options. Therefore the building is to be stick built to account for the congested site.

Figure 1 – Diagram showing the location of the 10m span IDL Link Bridge (highlighted in blue). Note the building underneath that restricts access to the location.

The proposed design can be seen in Figure 2 below. Due to the level of the bridge deck and the roof structure of the building underneath, the clearance of the top of decking and the top of the roof ridge is approx. 200mm. This has dictated the size of the beams that support the deck as can be seen in Figure 3 further on. This means that a traditional bridge structure where the deck beams are supported below is not feasible. The design therefore transfers the bridge loads from the deck through columns attached to two beams located above the bridge corridor. These connect to beams that span between the columns of the existing buildings.

Figure 2 – Drawing showing a section elevation of the IDL link bridge. Blue indicates existing structures, Black the IDL link bridge structure.

These beams have to carry not only passengers, but also electrical passenger vehicles (up to 5kN/m2). A 100mm concrete precast decking solution using Bison beams with a 50mm screed reinforced with mesh has been specified by the designer (see Figure 3 below – Bison beams specified in notes).

Figure 3 – Detail of elevation of the IDL link bridge deck structure

Here come the problems: According to the contractor, Bison are no longer able to provide the 100mm decking solution and this issue has gone back to the designer. A composite deck with steel profiling is not possible due to deflection limitations set out in the specification (limited to span/360). The designer claims that there are no suppliers who are willing to provide a solution and a redesign is required. However, having had a quick search of suppliers myself, there do seem to be some out there who can meet the spec – maybe the designers haven’t looked hard enough? I’ve not had chance yet to enquire with the designer about this.

From the client point of view there is a reluctance to change the design to accommodate a deeper decking. The first is that by increasing the thickness of the precast concrete decking slabs, the screed would be thinner; risking cracking issues if there are deflections. I would think that this may not be an issue as the precast decking would have pre-tensioned reinforcement? However, the spec (from Gatwick) states that crack widths are limited to 0.1mm and although this seems rather excessive, maybe this is a legitimate concern.

The second reason is that in changing the design thickness of 100mm, the designer would have a reason to add delays to the design of the bridge (which is already delayed and not yet finalised). As they are on a cost reimbursable contract (the reasons for this in itself are enough for a separate discussion!) any major design changes will incur a heavy cost. I think this may be why the designer hasn’t really investigated all 100mm decking options as there is no incentive for them to do so under this kind of contract. Instead I suspect they want to use this as a reason for delay to the design schedule by significantly changing the deck design.

As a side note there are also challenges around the temporary works and scaffolding required to enable the project. However, I think this deserves its own blog post so I’ll leave you on the edge of your seats for my next exciting instalment.

Categories: Uncategorized

Constructionarium

21/05/2019 2 comments

Summary.  I recently attended Constructionarium in central Scotland on behalf of Multiplex.  Here I acted as a client/mentor while Civil Engineering students from Glasgow University constructed scaled down versions of infrastructure and building projects.

Background.  The scheme is ran across the UK with a large number of universities and companies sending their students/graduates on it to develop practical construction experience.  Teams of approximately 12 are split into roles from project managers, setting out engineers and quantity surveyors and are given a set of drawings and specifications for their allocated project.  Alongside their allocated role they act as operatives while skilled assistance is provided by the training supplier such as plant operators and appointed persons.

Detail.  The event runs Mon – Fri and all the materials and equipment are provided by the supplier.  The team are not however informed exactly what they need and so it is amusing to watch them level ground with shovels for 3 hours before realising they could have requested a light wheeled tractor.  It is encouraged that the students are left to make mistakes as part of the learning process and simple problems like failing formwork provided platforms for discussion on structural analysis.  They are required to produce RAMs, obtain permits to work, conduct toolbox talks, inductions etc all in line with realistic outputs of a competent contractor.

constructionarium (4)

constructionarium (3)

Military relevance.  Constructionarium Scotland is a non profit organisation and the director was keen to promote its potential value as a training method for the military.  I have summarised some pros and cons below:

+  All inclusive cost for 1 week training is £150-200 per person (including lunch, eqpt + materials – minimum numbers are 20 people).   For context, 1 week pre deployment training (PDT) in Chatham for a B&SF costs approx. £750 per person.

+  Training can be tailored to suit learning objectives.  For example more experienced tradesman can be pushed in areas of planning, health and safety, resourcing etc.

+  One stop shop would make planning of the training straight forward.  Site is clear, free of contamination and includes welfare facilities and security.

–  Obtaining financial approval for training from Brigade may be difficult, even if justified as PDT.

–  Greater value was achieved through higher training numbers, for example we had 54 students and they could learn from different projects.  Engineer regiments may struggle to get this amount of manpower available for additional training.

–  Experiential learning training benefits are harder to articulate than straightforward courses.  For example a week’s PDT at Chatham for a B&C may include a scaffold ticket whereas Constructionarium did not include this type of validation.

– PDT may be better utilised practising construction directly relevant to the projects to be undertaken on deployment.