Archive
Writing an Effective Scope of Services – NEC3 Professional Services Contract
I’m currently in the process of preparing an Invitation to Tender for six sustainability consultants. My first task is to create a suitable scope of services within the framework of the NEC 3 PSC, which I’ve completed in draft form, I’m waiting out for feedback from the procurement and contracts manager. In the meantime I was wondering if anyone had any advice or experience they could share regarding writing an effective scope of services?
Any risk of a contract?
Background:
- Heathrow Airport use an overarching Framework Agreement (bespoke contract: target price, similar to NEC Option C) with a principle contractor (Mitie) for the supply of services.
- I am working within the Energy Demand Management Team that looks for one-off opportunities to employ novel technologies (energy efficient lighting, intelligent air-con control etc.) to make financial savings.
- These one-off works make use of a Works Package clause within the framework contract, where the contractor can be set to work under a simple Purchase Order (PO) agreement.
- These agreements follow the form of a fixed-price (NEC OptA) as they as it has been the simplest at the outset to manage. Although still subject to many of the payment and H&S clauses of the framework contract, there is no contractual obligation for submission of a works programme (by the contractor) or detailed project deliverables (by the client) beyond the scope that is given in the PO.
The potential problem:
- Although the projects are relatively small (6-10 weeks and typically less than £100,000) I think there still exists significant risk for both parties should there be time or financial issues.
- There already exists a good working relationship between the Client and Contractor but in this uncertain environment where the bean counters have most of the say, there may be cause for friction.
Where I come in:
I gather that it is probably rare to be given so much scope in an organisation! I am keen to play with different options and tailor the contract based on the scope definition of the individual work package and my own (and boss’) personal willingness for risk and admin. I am told I have the option to change the commercial model as per my requirement in any specific work package. I could specify any of Fixed Price (OptA), Target Price (OptC), Cost Reimbursement (OptE) or a combination of them.
Questions:
- My initial thoughts are to formalise the existing client/contractor relationship and to head down an NEC OptA route using NEC Minor Works contract.
- Has anybody else any experience of working with principle contractors on jobs of similar sizes/costs? Has there been any particularly good or bad experiences and what are the significant pitfalls to avoid?
Recent Posts
Archives
- November 2024
- September 2024
- August 2024
- July 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- November 2023
- October 2023
- September 2023
- April 2023
- March 2023
- February 2023
- January 2023
- November 2022
- October 2022
- July 2022
- May 2022
- April 2022
- February 2022
- January 2022
- November 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- November 2015
- October 2015
- September 2015
- August 2015
- July 2015
- June 2015
- May 2015
- April 2015
- March 2015
- February 2015
- January 2015
- December 2014
- November 2014
- October 2014
- September 2014
- August 2014
- July 2014
- June 2014
- May 2014
- April 2014
- March 2014
- February 2014
- January 2014
- December 2013
- November 2013
- October 2013
- September 2013
- August 2013
- July 2013
- June 2013
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012