Roy/Greg – I would be grateful if you could have a look in spons for the rate for Post Tensioing work, Supply and Install (somethign along the lines of a price /m of tendon or beam would be outstanding).
My Tender Plan is getting finalised and I start pre tender meeetings with the Sub Contractors on Tueday and I would like a starting point on price.
Many Thanks
Steve
Categories: Uncategorized
Stephen
Roy isn’t in work today and I don’t know which e-mail address he has post alerts sent to, but I have sent him an internal e-mail and one to his personal account advising him of your request.
Jim
HI Steve,
How did you get on with this? Roy tells me he sent info throught but heard nothing.
Richard.
Hi Roy, Richard,
Apologies for no response I thought I had replied – my mistake.
Rates were very helpful to give me some context prior to a Value Engineering session. They are now in my back pocket for when I get involved with the tender review….However this has been delayed as the client has taken issue with John Holland’s Terms and Conditions and put a hold on approving all new tender applications (the approval required before opening bids to the market),
This has been goign on for about 3 weeks so fingers crossed this will be lifted soon and I will be able compare prices and value before not too long!! The effect of this freeze on other packages is staritng to effect work on site so it will be interesting to see how this plays out!!
The aim for me is to get involved through tender to mobilisaton and installation…fingers crossed I will still be on site when they are needed!!
Many thanks
Steve