Home > Uncategorized > A journey of a thousand miles starts with a single step.

A journey of a thousand miles starts with a single step.

After 2 months of pushing and frustration we finally have a project that is under way.  Not bad considering the the Contractor was given notice to proceed in Oct 12.  The past few weeks have given me yet more insight in to the world of contract management and the ways in which contractors can try to extort money from seemingly watertight documents.

3 weeks ago during the Contrator’s biweekly (fortnightly) meeting it was announced that the Government (us) was sitting on over 53 late submittals (30 days old or over).  This seemed a little high so on returning to the office we all checked the register and the Contractor was right.  My mentor was on course, so taking the initiative I started tracking down the outstanding submittals with the design contractor.  They had not received any of these documents and some were now key to the project ever getting of the ground and I am not just talking about the scaffolding proposal.  On going to my mentor’s cubicle I discovered 95% of the documents under his desk where he had not finished sending them on. The situation sounds a lot simpler than the reality.  Although some were actually just very late in being processed (from December!) there had actually been a change in the procedure in early Mar 13.  The contractor had been instructed to change all submittals to electronic formats to be sent to USACE and the design contractors simultaneously to help save time and money rather than send us the big bundles of paper and documents sent previously.  Parts of these documents were sent electronically but the drawings had not because it was assumed by the contractor they had already been sent on by USACE as hard copies.  In an afternoon I was able to identify all the missing documents and FEDEXed them on to the design contractor for comment.  It was typical that the District Engineer had flown up from South Carolina that day and had to see all this but he was reassured that there was more to the slow progress than just the late submittals so we got away with that one.  The quality of the Risk Assessments from the Contractor continues to be poor and there is still a big question on how the drainage in the 90ft High Bay area is ever going to get installed as there is no room for any form of elevating platform.  Going through the roof would actually be good option!

As part of our CPD, Ben, Matt and me were taken by the head of Baltimore Construction Department to the Washington Aqueduct.  During the Civil war a project to divert some of the Potomac in to DC to provide a pressurised water source to down own areas was devised.  An aqueduct was created that sent water right in to town with pressure high enough to power the 60ft fountain outside the Capitol building.  The design has been refined over the years and now provides the potable water supply for DC, Arlington and two counties in Virginia.  We visited the purification plant that was designed in the early 1900’s.  The process is the same as those we learned about but now the site is fully automated and larger than the original concept.  It was interesting to see how the far the automation had gone – the whole system was monitored by two technicians – and there are extensive on site labs for checking water purity and biological contamination.

Tanks
Original Sedimentation Tanks

ponds
Holding ponds – 4 of them (with geese)

Pumps

Main plant pumps

We have also had the Chief Instructor and Senior Instructor over for their visit.  This was another good opportunity for us all to see Ben’s site in Fort Detrick, my site and Baltimore HQ as well as present to the PEW staff on our experiences and reaffirm that the US option is a great opportunity for future PET courses.

Meanwhile back on site work has finally started.  As of last Thursday two men are installing the conduit necessary to install the 24ft Big Ass Fans TM (That is the brand name not the nick name).

BA Fan

A Big Ass Fan TM

This is a huge psychological break through as up to now we were convinced this project might never start.  In a meeting with the client on the same day I put forward my value engineering proposal to the Client that the contractor should be able to use a roof lift that allows access to all the roof levels in the building without interfering with operations, as opposed to installing scaffolding stairs that will go 100ft up to the top level and be in place for 2 years. As expected I met resistance because of “legal reasons” but when pressed on what these were the answers were not convincing.  “What if they damage it or break it – we become liable” was the main argument so I suggested a waiver or on site agreement could over ride this concern.  Although not convinced the Client is prepared to let me investigate as he can see there is cost saving to be made.  I am in consultation with the legal department as we speak.  I also suggested we look at siphonic roof drainage for future projects.  This was the basis of my TMR and is able to reduce the cost of roof drainage (and the size of pipes etc) by over 40%.  The Client was very interested in this and is keen to get this looked at on the new warehouse buildings going up on site.  He suggested this system should also be introduced to the whole of USACE!  And to cap off a good week the Contractor was served a Letter of Concern stating that the progress is unsatisfactory and that they are due an interim grade of unsatisfactory for their progress to date.  As expected the reply was trying to blame us for all the issues but we have enough paperwork to prove otherwise.

And in other news:

We have just survived our first near tornado.  The Government alerts all went off telling us to get in the basement (typically the kids had just gone to sleep!) and we watched as the radar picture on TV showed a direct path of a potential twister to our district.  Fortunately nothing happened but three twisters did touch down nearby.  They were only small and apart from scaring some motorists, destroying a house garage and moving a car 6 feet, there was very little damage.  Also I have taken Warrick to is first Monster Truck show.  An interesting experience, not only for the trucks but also to see a gathering of the Red Neck Clans.

Road Kill Round Up:

3 deer

2.5 Racoons (the hot weather seems to be keeping them off the roads)

101 uses for the phrase “There you go” Pt 1– this is the Swiss Army Knife of East Coast phrases and covers a number of scenarios.  It can be used to mean the following:

1. You have arrived at your destination

2.  Here is the item you were looking for

3. I see where this conversation is leading

4. Well wasn’t that a fortunate out come

5.  Now I understand

6.  I think I know what you meant (but with some reservation)

7.  This is what I did and look what happened

8.  I think you have just answered your own question

9. Just like that

10. The job in hand is complete

11.  I can tell that was really satisfying

12. That was the end of that

Until next time.

Categories: Uncategorized
  1. coneheadjim's avatar
    coneheadjim
    17/06/2013 at 6:53 am

    Nick

    The water teatment plant looks to be pretty conventional. Were they limited in what they could do to upgrade it by the history of the site?

    Jim

  2. nickyboy77's avatar
    nickyboy77
    25/06/2013 at 1:55 pm

    Hi Jim,
    The site is very limited in size as well as history. It is actually on the corner of the square DC boundary (a stone from the 1700’s marks the spot 70m from the main building) so could not be expanded on that reason alone, but the ground around the site is now well developed. They have created two further reservoirs down stream which now account for the extra demand in the area and come with their own processing facilities. All are still fed via the aqueduct.

  1. No trackbacks yet.

Leave a comment