Home > Uncategorized > Headache

Headache

Clair Manifold Support Bracing

I have been trying to schedule this small piece of work for the last two months. I originally had it in the plan for December to execute during a well head maintenance period. Due to taking on the Clair coolers and the number of issues we saw at the close of that project, this one wasn’t ready for delivery. 

Front End Loading

This particular job is the final part of a larger project to standardise the supports on the production manifold on Clair. Development of wells is such that this had been developed somewhat ad hoc, with each flowline or group thereof being a separate project and therefore subject to different design in the supports. In 2011 the standardisation piece was completed but a Project Change saw the development of additional cross bracing to reduce vibration resulting from the modifications. The vibrations are not so severe as to threaten integrity, but it is something that should really be address when considering preserving the long term integrity of the system.

 Image

(Above – T support on the production manifold)

(Below – Proposed new bracing to these T supports)

Image

 

The bracing itself is not the issue, it does not breach containment and is affixed to the primary bracing. It is all drilled and bolted and therefore can be installed during normal production. However, the bracing results in a clash with the existing temperature sensors which requires for them to be removed and replaced with longer stems. The manifold cannot be flowed while these transmitters are removed. A simple probably £20-50k project is stalled because to run it in isolation would cost around a days production, 30,000 barrels at $100….

This part of the wider project was developed as a project change when it was identified that the new supports would not mitigate against vibration effects sufficiently. So the initial Define was not completed properly, that much is clear. This has been compounded because the project change has been developed with no thought to the schedule implications of replacing the transmitters. It is clear from the Workpacks and the WGPSN plan for the work, that an assumption was made that the transmitters could simply be replaced prior to installing the new bracing. I can find no evidence that any other solution was looked at for this problem. I would have thought that connecting the horizontal part of the T supports and diagonals down to the floor from there would avoid any clash and if can’t schedule this project into a planned outage, then I will be recommending that the project goes back into Define to better understand and develop a solution.

Time is Money

The hardest part of this process has been finding the right person to discuss the problem with to identify a way forward. The only planned outages generally fall into the category of TAR (Turn Around) or Wellhead Maintenance. There is no way that this work would get into a TAR, and if it did it would be the first to get thrown out again. The well head maint period is my best bet and they happen about twice a year with individual wells taken off-line for various workscopes to get completed. Clearly, no engineering manager is overly enamoured of the idea that I parachute some extra work into their plan and getting traction with the Wells team has been tricky. I now have the ear of the Wells team lead and I am hoping to get to a definite yes or no (expecting a no).

Bottom Line

This is probably the least important piece of work I have going on at the moment, but it is causing a disproportionately large headache. As an engineer, design should never take place in isolation, even if an SOR or other such mandate imposes project limitations, surely we must be professional enough to look beyond these boundaries for complications that the original author may not have foreseen?

Categories: Uncategorized
  1. Richard Farmer's avatar
    Richard Farmer
    10/12/2013 at 10:06 am

    looks like a belt and braces bluff to try to fix an ill defined problem. Think it might be wise to go back to finding out what the vibration issue is actually about before trying to design any structural solution. I’d hope the Wells team say no.

  2. lightstudy's avatar
    lightstudy
    10/12/2013 at 10:36 pm

    As do I. I have a meeting tomorrow with the Wells Team leader so I will finally get the right detail for the schedule. I’ve already got a survey booked to re-analyse the extent of the residual vibrational issue (post standardisation). The original vibration was so bad that the supports could not be constructed with the pipes being live due to the risk of loosing appendages between pipes, supports etc. I gather the supports have done their job, but I am yet to find the background for this cross bracing. I’ve already outlined a plan to kick the project back into Define to reanalyse the problem and the solution and this has had tacit support so far.

  3. Chris Marris's avatar
    Chris Marris
    08/11/2017 at 11:28 am

    Not sure if you are receiving updates but you will be pleased to hear that this issue is still not rectified. The project is still open, there has been different approaches used since, resulting even more differences in pipe support. I have recommended that a holistic study is conducted to either accept the current supports or reject and reignite the project.

  1. No trackbacks yet.

Leave a reply to Chris Marris Cancel reply