Home > Uncategorized > Importance of Understanding

Importance of Understanding

Importance of Understanding

Option 2 – Cofferdam construction sequence.

Categories: Uncategorized
  1. 20/03/2014 at 2:08 pm

    I’m quite intersted in this sequence: at stage 2 you seem to get a prop but I’m not sure how it would be placed?
    Stage 3 seems to be a displacement fill…so the stage 2 prop seems unecessary
    Stage 5 looks a bit odd unless you’ve excavated/ cropped, excavated cropped and then backfilled?
    At stage 10 you flood to keep the sheet but at stage 11 the sheets seem to have been cropped on the riverbed do-able with divers but I’d guess you’d just vibro them out from a barge

    …..contractor’s option 2 you say …paaaah!

  2. richphillips847's avatar
    richphillips847
    20/03/2014 at 2:20 pm

    I’ve cut the notes off this version to allow it all to go on one page. There is a jetty around three sides of the cofferdam at this point but omitted for clarity. Stage 2 is actually a tie to stop the cofferdam collapsing outwards when a piling rig is put on top of it. The cofferdam should be water tight at this point and so water can be pumped out and the tie (I’ve put forward the idea of it be capable of being both tie and strut depending on construction stage) installed from the jetty, yes you will probably need a man in a boat or a working platform hung off the sheets perhaps.
    Stage 3 – Prop is a tie for Stage 4, which may or may not be needed.
    Stage 5 – Again a victim of cropped notes, concrete terminated just above required level, then casing removed, then hole backfilled before excavation.
    Stage 10 – Sheets either burnt off by divers, realistic in my mind or extracted as you say BUT the pile cap is cast against the sheets greatly increasing the friction to try and pull it out in my view.

    I still think my initial option was practical although I accept that piling from a barge may prove prohibitively expensive, but the sheets can be smaller as you use the water and tides to benefit pumping and equalise pressure.

  3. Richard Farmer's avatar
    Richard Farmer
    20/03/2014 at 5:03 pm

    Like it. If you consider casting up against your piles will make extraction difficult why not space off them a little with some internal formwork? Must be cheaper than paying for divers and losing the piles?

    • richphillips847's avatar
      richphillips847
      20/03/2014 at 8:11 pm

      Richard, I don’t know the answer to that though I feel sure it must have been considered and discounted. Most of the permanent works have been presented to be as a fait accompli, I’ve just been considering the temporary works. I do wonder if it’s to do with scour protection, but probably not as the contractor would like to get them out. Once again many of the DS points raise the issue of only being told what you need to know for a very specific element of a job (have you worked out I have a problem with matrix structures yet?)

  1. No trackbacks yet.

Leave a comment