Home
> Uncategorized > Importance of Understanding
Importance of Understanding

Option 2 – Cofferdam construction sequence.
Related
Categories: Uncategorized
Leave a comment Cancel reply
Recent Posts
Archives
- November 2024
- September 2024
- August 2024
- July 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- November 2023
- October 2023
- September 2023
- April 2023
- March 2023
- February 2023
- January 2023
- November 2022
- October 2022
- July 2022
- May 2022
- April 2022
- February 2022
- January 2022
- November 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- November 2015
- October 2015
- September 2015
- August 2015
- July 2015
- June 2015
- May 2015
- April 2015
- March 2015
- February 2015
- January 2015
- December 2014
- November 2014
- October 2014
- September 2014
- August 2014
- July 2014
- June 2014
- May 2014
- April 2014
- March 2014
- February 2014
- January 2014
- December 2013
- November 2013
- October 2013
- September 2013
- August 2013
- July 2013
- June 2013
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
I’m quite intersted in this sequence: at stage 2 you seem to get a prop but I’m not sure how it would be placed?
Stage 3 seems to be a displacement fill…so the stage 2 prop seems unecessary
Stage 5 looks a bit odd unless you’ve excavated/ cropped, excavated cropped and then backfilled?
At stage 10 you flood to keep the sheet but at stage 11 the sheets seem to have been cropped on the riverbed do-able with divers but I’d guess you’d just vibro them out from a barge
…..contractor’s option 2 you say …paaaah!
I’ve cut the notes off this version to allow it all to go on one page. There is a jetty around three sides of the cofferdam at this point but omitted for clarity. Stage 2 is actually a tie to stop the cofferdam collapsing outwards when a piling rig is put on top of it. The cofferdam should be water tight at this point and so water can be pumped out and the tie (I’ve put forward the idea of it be capable of being both tie and strut depending on construction stage) installed from the jetty, yes you will probably need a man in a boat or a working platform hung off the sheets perhaps.
Stage 3 – Prop is a tie for Stage 4, which may or may not be needed.
Stage 5 – Again a victim of cropped notes, concrete terminated just above required level, then casing removed, then hole backfilled before excavation.
Stage 10 – Sheets either burnt off by divers, realistic in my mind or extracted as you say BUT the pile cap is cast against the sheets greatly increasing the friction to try and pull it out in my view.
I still think my initial option was practical although I accept that piling from a barge may prove prohibitively expensive, but the sheets can be smaller as you use the water and tides to benefit pumping and equalise pressure.
Like it. If you consider casting up against your piles will make extraction difficult why not space off them a little with some internal formwork? Must be cheaper than paying for divers and losing the piles?
Richard, I don’t know the answer to that though I feel sure it must have been considered and discounted. Most of the permanent works have been presented to be as a fait accompli, I’ve just been considering the temporary works. I do wonder if it’s to do with scour protection, but probably not as the contractor would like to get them out. Once again many of the DS points raise the issue of only being told what you need to know for a very specific element of a job (have you worked out I have a problem with matrix structures yet?)