The Coffee Cup
As the summer weather sets in construction of a new part of the campus begins and I have been given the responsibility of ‘Structural Lead’ for what will eventually be a Central Utilities Plant (CUP) building which will provide the cooling loads for the buildings on site. The structure itself is around 55m x 65m and is a steel braced frame construction sitting on a mixture of shallow concrete strip and pad foundations. The exterior will be clad with insulated metal panels, with one of the elevations detailed so that it can be disassembled at a later date and expanded, as and when the campus is expanded. This bit of the design echoes the nature of the entire project, which is expansion and longevity of the campus. The site is located on what will be called Coffee Road, and so some of the funnier members of the team have taken to calling it the Coffee Cup. All of the footings have been poured, with base plates set into them onto which the steel columns can be placed. Late last week I conducted a random check on some of the steel that has been delivered to site and cross referenced with the shop drawings whilst the contractor who is responsible for constructing the CUP structural steel surveyed the base plates to ensure that the concrete contractor had placed them in the correct location. All but one were approved on the as-builts and so work has just started erecting the steel, with an RFI submitted with regards to the erroneous plate. I had a slightly harder time however because for some reason the numbers on the steel work corresponds to the field set of drawings, which in turn do NOT correspond to the shop drawings. Quite why is a mystery however after much panicking I got to the bottom of the issue and the simple one man task became a difficult two man task with me cross referencing field drawings and shop drawings in order to ascertain which bit of steel we were looking at and whether or not it was correct.
Note also the lack of scale, which was initially confusing. The upper and lower holes are separated by c. 10”
Concurrently to this the concrete Slab on Grade (SOG) is being poured, with the second of four (2/4) pours complete already. The SOG is 6” thick with minimal bottom reinforcement and so the QA checks were fairly simple. An earlier RFI for the masonry walls location caught me out however as the approved reinforcement detail for the starter bars at these locations was drilled dowels, to be installed at a later stage, as opposed to what was shown on my field plans, which is the normal bent rebar protruding upwards.
Mostly the pours went well but I saw an impact on the project which some of you may or may not have come across, but which is very difficult to mitigate.
About a quarter way into the 2/4 SOG pour at the point of the second slump test there was a recorded measurement of 11”. This is 2” out of tolerance and should have been caught as the first concrete came down the chute and into the pump. It is at this location where the first of arguably three slump tests is taken.
The worker here, who works for a third party QC contractor, is hugely experienced and can estimate to within a half inch what the slump of the concrete is. The reason I say that there are arguably three slump tests on the concrete is because as it comes down the chute he is supposed to estimate whether the concrete is compliant or not; if not the truck is immediately told to cease pouring so that only minimal deficient concrete enters the pump. This is done because the actual slump test cannot be conducted on the first 10% of concrete in accordance with ASTM C172 and ASTM C143. In short the issue is that the contractor at the chute should have identified the fact that the concrete was deficient. Instead he had given a positive reading to us that the slump was only 8”. Some might call this a lie.
As it turns out there is a bit of history with the worker in question who is, by all accounts, a disgruntled employee for reasons which I won’t go into here. Since it was too late to turn the truck away at this point and deficient concrete had already been placed it was noted exactly where the deficient concrete went in the slab (2 locations) and additional cylinders were ordered by the Principal Contractor. It is anticipated that these will close out the deficiency when tested as the slab is only rated at 4500psi (30N/mm2) and most of the tests come out higher than spec. but if not then core samples will be taken and the way forwards decided from there. Since the incident the worker in question is closely supervised. I’m not sure of the politics but to my mind he is tying up additional manpower and should probably be re-tasked.
Away from this I have had my first Health and Safety impact on site. The issue was to do with a slope stability problem next to one of the haul roads which runs adjacent to a sizeable chiller pipe chamber (essentially a big hole) As I was driving from the Coffee Cup back to the office I noticed that the batter angle on the slope was near vertical, and that there were track marks right on the edge of the road. I recognised the signs of a slope failure which I attributed to reduced shear strength of the soil (due to afternoon deluges we experience) and surcharge (of the tracked plant). My concern was that given the location of the tracks, which were right on the edge of the haul road, and the location of the haul road with respect to the gaping hole that a vehicle could easily cause further failure and would subsequently topple into said hole. I called the Principal Contractor who agreed to ‘have a look’ at the area. They obviously agreed with my assessment as the road was re-graded the next day and concrete barriers were placed along the edge of the road to prevent vehicles tracking too close to the edge again.
In other news
My car MPG is noticeably lower of late. As I’ve mentioned the weather is hotting up. The only reasonable explanation, from an E&M point of view, is that this has caused the many thirsty horses under my ‘hood’ to become thirstier. It did pass a rigorous 5 minute annual emissions test though. I’m not sure how, I can only assume that the test is to verify that it does have emissions.
I also recently participated in ‘Organization Day’ which marked the 240th birthday of the USACE, which is two days older than the Army apparently. It was a good day out with ‘soccer’ and volleyball tournaments. I was more use to the soccer team, with 2 goals helping ease the RSFO team to the trophy. Unfortunately I did little to halt the demise of the volleyball team, losing as we did 25-9. Good ‘cook out’ (BBQ) though.




Why are they using drilled dowels in that location? What’s the bar diameter and drilled depth? Seems odd that it would be designed drilled. We only drill if the contractor has forgotten to install some bars or if the design was changed too late – so most days then!
Is your increase in fuel consumption aligned to an increase in AC use?
Where will you go into the detail about the disgruntled employee?
The drilled dowels are as a result of a submittal, not design. The design called for the rebar to be installed prior to the SOG being poured however the Principal Contractor requested a drilled and epoxy method for reasons of practicality and H&S. There is a lot of steel erection going on around the locations where they were to be installed and there was concern that bars protruding every 48″ (at certain locations) would either get knocked about too much or just be hazardous. The bars are #6s (3/4″ dia) and will be drilled to a depth of around 6-3/4″. You can check out the following site, we are using HIT-500 epoxy. https://www.us.hilti.com/volume-calculator
Increased fuel is definitely thirsty horses. AC is on all the time anyway.
The disgruntled employee is hugeley experienced and actually fairly well respected for his technical competence – I think he has some health issues which he doesn’t feel are being addressed by his company (and there may be other underlying issues also). I havent seen him for a day or two now, but not sure where he is. Last pour I was at he had an oppo to help him out, but I think that was at the behest of the Principal Contractor who wanted to make sure he was supervised.
Brad – Are there some roof beams missing on the far bay?
What is the soil type of the haul road? How does the drainage from it occur, chamber/v ditches?
Is the haulb road accounted for in temporary works documents and does it have a periodic inspection requirement?