Home > Uncategorized > Oz NDY – From One Hospital to Another.

Oz NDY – From One Hospital to Another.

Introduction

I’ve now been in the design office for 2 whole weeks, working in the Interiors/Tenancy Section in the Existing Buildings Department. In summary, we design all mech, elec and hydraulic services for existing building refurbishments, usually office/business fitouts. Overall office work leading up to Christmas has been a little frantic, mainly involving clearing deadlines and getting tenders out for new business for the start of the New Year. I have undertaken a few interim tasks as stated below with my first real project role coming in the form of an animal hospital fitout – kind of apt coming from the PCH project.

Interim Tasks

The following three tasks were given to me as more of a filler and introduction to the types of projects I’ll be getting involved in.

  1. Fee Proposal Review. A review of NDY’s fee proposal for the replacement of a generator exhaust. The mechanical contractor originally approached by the client were only a small company and felt the proposal was too detailed and consisted of too much management terminology for the simple requirement. There was nothing wrong with the proposal and we deemed it fit for purpose so advised the client to explain this to the contractor. If they still didn’t agree then we advised them to re-tender to a more suitable one; who could see past the management procedures and policies, that I feel they were deeming too complex.
  1. Giving Technical Advice via a Consultant’s Advice Note (CAN). The CAN was for the reprogramming of the BMS in a recent office fitout we had completed where two separate floors were adjoined by a central stair. The CAN gave a technical explanation for the need to consider both floors as one in terms of smoke management in a fire event when creating the fire and smoke cause and effect matrix.
  1. Restricted Return Air Path. This consisted of a study of the AHU return air path in a new office fitout where, due to the type of return air system used, being via extract grilles straight in to the ceiling void acting as a large plenum, it was found that obstruction from sections of full-height partition walls were restricting return airflow. We came up with a solution to install a number of transfer grilles through particular sections of the full-height walls. The trade off being potentially increased noise levels for better recirculation.

Short-term Projects

I have just started my first main project, my role being the Project Leader (PL) for the fitout of a new animal hospital. The current space if no more than an empty warehouse serviced by 3 No. Evaporative air-conditioning system linked through flexible ducting (which they seem to love over here). There is also an existing toilet and lighting throughout.

The PL roles sees me being the client facing project manager reporting to a Project Director (PD) who is also doubling-up as the mech technical lead. My boss (also mech biased) has been helping out and accompanied me to my first client meeting and site inspection; he will be on extended leave post Christmas till the end of Jan so has basically helped me get the project rolling.

In terms of detail at this stage our client, Perth Citi Fitout, are the Managing Contractor who have already put together construction force of various subcontractors based on the scope of works from their client, Vetwest. They have Nagel, architects, who have designed the fitout so we have a pretty good idea of what they want. The services are pretty straightforward with the bulk of design work being the mech air-conditioning system.

At present the MC has budgeted for a complete strip-out and new installed system so that’s exactly what we are going to design. We did see if the existing evap units might be useable but decided pretty quickly to replace them. This was mainly based on the poor effectiveness of evaporative cooling in high humidity conditions. Granted that the Perth climate conditions produce mostly dry heat but there are occasional humid spells in the winter months, which realistically would only offer a small delta T due to evaporation becoming more difficult proportional to the water content present in the air.

The MC issued us a concept mech layout but from our meeting and discussions over the number of HEPA filtration units required we went away and conducted our own research. The two main points were, the requirement for a grease trap for the wastewater drainage system and HEPA filtered units to be installed in all locations where animals would be.

Both of these are being investigated and I am awaiting specialist confirmation. My initial thoughts being thus:

Grease Trap. After stakeholder engagement it was identified that the areas where animals (primarily dogs) will be kept for long periods of time, the kennels and cages are fitted with special chemicals that soak up urine and water content in faeces. These are regularly cleaned out and disposed of in specific excrement waste bags so it is my view that normal wastewater drainage will be suitable. Of course the Water Corps may have a different view and I also need to check the Building Code of Australia (BCA) Guidelines.

Multiple HEPA Filters. Again after stakeholder engagement it was found that Vetwest are wishing to apply to the Australian Veterinary Association (AVA) to seek accreditation of their hospital accreditation scheme. The Vetwest proj mgr stated that under the AVA’s standard they required all air-conditioned spaces where animals are present to be HEPA filtered. It was evident in the mtg that they didn’t actually know how this worked as they were talking about mixing normal supply air and HEPA filtered air in the same space – which obviously negates the very clean air provided by the HEPA filters. What we did know was that just like in a human hospital the surgery room needs to be supplied by HEPA filtered air but I don’t think other areas do. To confirm I researched the AVA standards and found nothing relating to HEPA filtration at all so posed the question to one of their standards testers – I’m awaiting a reply.

NDY’s Concept Design

With these answers outstanding I cracked on and came up with a concept mech (air-conditioning) layout. I split the space into four zones and plan on using 4 No. Packaged DX Units (yet to be specified). These DX units will be mounted on the roof (where there’s plenty of space) and consist of ridged ducting for the main run with flexible ducting to each supply air grille. Figure 1 shows the draft concept design. This along with a Consultant’s Advice Note (CAN) explaining our justifications for the system type will be finished off and sent to the MC for comment before Christmas.

Post Leave Continuation

On my return from leave and after consultation with the MC over our concept design I will then begin the detailed design. This will initially consist of using a software package called Trace which gives you heat load calculation so I can then size my packaged units. I’ve had a quick play with it already and it’s very similar to Hevacomp but with more experience I’ll try and draw out some more detailed comparisons. Then I’ll have to size all the ductwork to achieve the correct flow rates etc that will lead to cost planning. At the moment the MC has quoted AUD $55k for 3 No. units and our 4 No. Packaged DX Units is looking around the AUD $70k mark. I will then move on to the hydraulic system, mainly consisting of a reticulated Oxygen supply and Suction system.

Project Reflection

Being part of the Interiors/Tenancy Section means that I will hopefully have a number of short-term design projects to PL on. This will provide me with a good basis for reflection and help steer subsequent projects in order to build on my professional development and focus on any outstanding UK-SPEC requirements.

Untitled1

Figure 1. NDY Concept Mech Layout

This just leaves me to say I won’t be blogging for about 4 weeks as I’m now on Christmas leave…have a Merry Christmas and a Happy New Year!

Categories: Uncategorized
  1. Rich Garthwaite's avatar
    Rich Garthwaite
    21/12/2015 at 9:19 am

    Fran,

    Why were your transfer grilles going to lead to increased noise? Is it due air velocities through the grilles or noise transfer from one room to another? Are you limited on the number and size of transfer grilles you can install?

    • Fran Rizzuti's avatar
      Fran Rizzuti
      21/12/2015 at 9:35 am

      Rich,
      The noise mainly comes from one room to the other and the reason they are shaped like two opposite dog legs (think also one half of a swastika) and can also be lined with acoustic material, but clearly not as sound proof as the wall.

      The only limit to the size and number of grilles boils down to cost and free space between services that go through a sealed penetration.

      My recommendation was to use a combination of the types already installed as they could purchase from the same manufacturer and hopefully get a discount. Though there was one penetration that was outside these; here it may be a case of just leaving as an open penetration thus saving the cost and time of installing a transfer grille – as long as the noise levels are acceptable. In fact, it may be possible to create the holes first and test the noise levels before installing any further transfer grilles and if ok leave it at that. The issue with this is the added labour cost of the likelihood of having to pull down sections of ceiling for a second time to install the grilles if noise levels are too high.

  2. Rich Garthwaite's avatar
    Rich Garthwaite
    21/12/2015 at 12:33 pm

    So is that a design that NDY have worked through from the start or are you picking up on work done by another firm? If you have to put in acoustic tiles who will pay?

    • Fran Rizzuti's avatar
      Fran Rizzuti
      21/12/2015 at 2:07 pm

      It’s work NDY have done from the start but obviously didn’t think about the return air path being slightly blocked. So yes, NDY will have to foot the bill. What makes it worse is that the building is now occupied so additional works will need to be carefully timed, likely being conducted out of hours thus costing more.

      • Rich Garthwaite's avatar
        Rich Garthwaite
        21/12/2015 at 2:52 pm

        Better to find out now rather than later. Carillion’s head office in Wolverhampton (why would you have a head office in Wolverhampton?) was having major issues with the VRV heating / cooling system due to a similar issue; down stand beams occupied the ceiling void /plenum, the gap between the down stand beam and the ceiling had then been filled with insulation making a nice barrier to air flow.

  3. 21/12/2015 at 2:10 pm

    Assuming the MC is on a design-build contract Fran are the turn around times pretty tight for you? Do you have an idea of when construction starts and might you get to see your units installed? Or even just bought and craned in?

    • Fran Rizzuti's avatar
      Fran Rizzuti
      21/12/2015 at 2:16 pm

      I haven’t seen many details on the MC’s contract with the client but usually in these types of interior jobs we turn around our design within 3 – 4 weeks with the whole project being done and dusted in 3 months. Basically once our main design is fixed we will keep a listening watch and offer design assistance to the MC throughout their build.

      • Rich Garthwaite's avatar
        Rich Garthwaite
        21/12/2015 at 9:21 pm

        If you’re turning round the design in 3-4 weeks and the job is relatively straight forward (fitting out a big empty box) why is the client electing for a D&B contract over a traditional?

      • Fran Rizzuti's avatar
        Fran Rizzuti
        21/12/2015 at 10:06 pm

        Rich, like I said I haven’t seen anything on the contract side of things yet. I’ve only been working on the project for two days before going on leave and that was focusing on getting our concept design out. However, the building owner/occupier is a veterinary chain and don’t know much about building design hence the design and build type contract. The design is straight forward in terms of the mech, elec and hydraulic services required compared to other projects but it’s still overall, construction wise, requiring a MC to manage the works; not sure if you can make out the detail on the draft concept design.

  4. 28/12/2015 at 1:24 pm

    Rich,

    I assume that the 3 – 4 week turnaround is in part because it is a D&B and co-ordination is less of an issue. As the risk is with the contractor they will ultimately be happier to make decisions on elements or get them straight from the designer, as they have a direct contract with them. The alternative might involve a more convoluted RFI chain via the client to get to the designer for small stuff, which is what I have seen here to a degree. This then slows down the job.

  5. 04/01/2016 at 8:29 am

    Fran,

    Your deliberations over where you would be best to go on phase 3 have returned dividends; this is an exemplary intorduction package to a cionsultancy role. We always used to put new engineers onto checking and proposal reviews so they could see how we set up our designs and business then take them along to design team meetings before releasing them onto a relatively straight forward design project. Next learning points after filing the calcs were accounting for time, invoicing the client and dealing with RFI’s without going over budget!

    I think the biggest challenge when starting out in the design office is usually accepting that about right is good enough rather than spending a large amount of client paid for time striving for perfection. My experience says that about 6 jobs on the go in rotation at any one time is about the norm and the challenge is minimum time and effort to keep the plates spinning!

    Hope you enjoy your extended leave.

    • Fran Rizzuti's avatar
      Fran Rizzuti
      15/01/2016 at 12:55 pm

      Richard,

      I am already learning from the early stages of this, my first project, a fair amount already. And like you say I can see the work load, through being tasked with elements of concurrent projects, intensifying quite rapidly. Very true reference accepting ‘close enough’ being good enough, especially for submitting concept designs; as experienced just this week.

  6. 13/01/2016 at 9:58 am

    Fran

    Hope the leave is going well. What standards are used in the oxygen/vaccuum designs over there? With talk of a surgery room there will presumably be more gases being supplied than just the two?

    • Fran Rizzuti's avatar
      Fran Rizzuti
      15/01/2016 at 1:02 pm

      Mark,

      Being a veterinary hospital the only requirement for medical gases is oxygen. It’s to be supplied to the surgery as well as the treatment and X-Ray rooms. There is also a suction requirement from the surgery and treatment rooms for any bodily fluids etc. As for the standards, I will be digging into them for the more detailed design along with the hydraulic engineer. At the moment all I have completed is the concept design.

      • Fran Rizzuti's avatar
        Fran Rizzuti
        18/01/2016 at 2:43 am

        Mark,

        In terms of Australian Standards used for Medical Gas systems the main one is AS 2896-1998, but there are a number of others pertaining to specific parts of the overall installation.

  1. No trackbacks yet.

Leave a reply to Fran Rizzuti Cancel reply