Home > Uncategorized > Have you got a spare £2,915,000 for a 3 bedroom apartment?

Have you got a spare £2,915,000 for a 3 bedroom apartment?

I started last week on the South Bank Tower in London with Mace Group. Normally as PET students we work with a principal contractor that will actually do some construction themselves. Not so with Mace. As a construction management contractor, they are the principal contractor but all works are sub-contracted. With staged tendering throughout the project this means the client gets the best deal (theoretically).

South Bank Tower

What does this mean for me?

Will I get enough experience to get through CPR? Well I believed so before the attachment and I still do so now one week in. The post I have assumed is Assistant Construction Engineer. The Construction Engineer and I are responsible for all temporary works on the site, and also all Mace sites south of the River Thames including the Tate Modern extension. My principle focus is the Tower, but as with all sites there are lots of problems that need temporary works input.

Some background to the site.

CIT Group purchased the South Bank Tower in a joint venture with Jadwa Investment (a Saudi investment company) in June 2010. Since then KPF were contracted as the Architect and Adams Kara Taylor as the Design Engineers.

Works include a 12 storey extension on the existing brutalist designed 30 storey reinforced concrete tower block built in the 1970s by John Laing Construction Limited.  This will be mixed office and residential space.  Apartments start from £900,00 for 1 bedroom.  The podium building (with commercial space) at the base of the Tower will have a 3 storey extension.  There is a new basement, as well as a link span between the podium and the Tower.

SBT Main works

Towards the middle of next month J Coffey (sub-contractor for the core reconfiguration) will complete all works up to level 30. This will allow PC Harrington to setup their slip forming rig, and hopefully start slipping at the start of April.

The designers (Adams Kara Taylor) have not designed for any temporary states during construction. They only ‘do’ the finished article and check temporary works plans as satisfactory. So, on my plate I have the erection of Tower Crane 4 (TC4) on level 42 to plan once the slip is complete, tying Tower Crane 1 (TC1) to the core at levels 28 and then 34, the temporary works on the basement (that is remarkably like Ex Cofferdam), core alterations to the podium buildings to consider, the foundation plan for tower crane 3, and the grillage design for a crane on top of Lambeth Met Police Station.

So in conclusion:

I understand this is a different approach I am taking to Phase 2, as I am not directly managing a task, but there is plenty of opportunity for me to do this later in my 10 months. Right now I am learning; the complexity of the project, the real engineering language that civilians use, applying my understanding of engineering and attempting to do so in a time efficient manner.

Categories: Uncategorized
  1. richphillips847's avatar
    richphillips847
    26/02/2014 at 5:05 pm

    I’m sure I’m about to get told off but I can’t see there’s any problems with it. We’ve worked for main contractors where you tell the project manager of the sub contractor to do something differently or re-do it, you never really directly manage bodies not like we’re used to the best you can hope for is a kind of OPCON arrangement. Whilst your title doesn’t perfectly fit it sounds somewhere around the temporary works coordinator which gives you a good shot at experience.
    I was lucky being on a design and build contract so I could find out what had gone wrong when things failed, in Mace’s elevated position you may find it difficult to get the same kind of clarity as the contractors will try to keep their dirty laundry hidden.

    • rrohall's avatar
      rrohall
      03/03/2014 at 5:44 pm

      You are not wrong there. In the two weeks I have been here a few issues have come to light that the sub contractors hoped might not have! What about the ones we don’t even see!

  2. painter789's avatar
    painter789
    28/02/2014 at 7:33 pm

    Rich

    Have no worries – what is important is that you are on site and involved with temporary works. The project will give you more than enough experience and will certainly get your reviewers talking about another 12 storeys on top of an existing building. There loads of issues to discuss. On on on

    Kind Regards

  3. 07/05/2014 at 8:53 pm

    Rich

    An interesting project, just a shame its yet another development out of the reach of most of the population of the UK, let alone London!

  1. No trackbacks yet.

Leave a reply to rrohall Cancel reply